METHOD STATEMENT SETTING CONTAINER OFFICE
Key Plant and Tools Required: - Mobil Crane 7 ton - Webbing Sling 3inch - Shackle @3/4 Key Materials Required: - Stone - Wood - Sand - Fence pole - Cement - Steel Plate - Concrete pipe - BRC Other Essential Equipment: - Barricade Tape Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s)) - Spinal cord injury when lifting up cause failure of body position - Slip/fall when up/down the crane - Sling broken/improper - Crane nudging/bumping a worker/vehicle/heavy equipment - Rigger fell from above over 1,8 m Specific Staff Training Requirements: - Certified rigger - Certified crane operator - Certified and inspected crane Sequence of Operations: (Specifying methods of working, tools, materials and equipment utilized) 1. First, set the area for office container and logistic container, and set the pedestal made of coconut wood in the desired area. 2. Mobile crane will be positioned on the desired area 3. Trailer truc...