METHOD STATEMENT SETTING CONTAINER OFFICE

 Key Plant and Tools Required:

- Mobil Crane 7 ton
- Webbing Sling 3inch
- Shackle @3/4

Key Materials Required:
- Stone  - Wood
- Sand - Fence pole
- Cement - Steel Plate
- Concrete pipe - BRC

Other Essential Equipment:
- Barricade Tape


Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s))
- Spinal cord injury when lifting up cause failure of body position
- Slip/fall when up/down the crane
- Sling broken/improper
- Crane nudging/bumping a worker/vehicle/heavy equipment
- Rigger fell from above over 1,8 m


Specific Staff Training Requirements:
- Certified rigger
- Certified crane operator
- Certified and inspected crane


Sequence of Operations:
(Specifying methods of
working, tools, materials and equipment utilized)
1. First, set the area for office container and logistic container, and set the pedestal made of coconut wood in the desired area.
2. Mobile crane will be positioned on the desired area
3. Trailer truck will come to the office are bring 2 sets of 20 feet container (office container and logistic container)
4. After both of mobile crane and trailer set in their position, lifting work can be started
5. Ensure the rigging activity following the rigging plan, certified rigger needed. For rigging material using four pieces of web sling 3”.
6. Lifting activity can be started, SWL procedures must be followed. In this lifting activity will use 6m boom from mobile crane.
7. Set both containers in the desired position.

Comments

  1. Container liners are an efficient packaging solution designed to protect bulk goods during storage and transportation. They transform standard containers into cost-effective bulk packaging systems, ensuring Container Liners suppliers in delhi product safety, and reduced contamination risks. Widely used for agricultural, chemical, and industrial products, container liners help minimize losses, improve logistics efficiency, and maintain product quality from origin to destination.